The Loughs Agency has investigated two incidents at a wind farm under construction in Donegal, after a rock berm was breached and dirty water was separately discharged into a nearby watercourse.

The incidents occurred at Drumnahough Wind Farm, a 56MW project being developed jointly by SSE and FuturEnergy Ireland.

The first incident, involving the breach of a rock berm, occurred on Thursday, 17 September. Material moved beyond the berm and onto a lower embankment area.

ADVERTISEMENT

Response

A spokesperson for Drumnahough Wind Farm DAC said: “An incident occurred last week at the Drumnahough wind farm construction site during which a rock berm was breached, resulting in the movement of material beyond the berm and onto a lower embankment area. No one was injured and there was no impact on personnel.

“In line with established safety procedures, the affected area was immediately secured and made safe. Works in the vicinity of the incident have been suspended while it is assessed and managed by on-site engineers and environmental specialists. Precautionary measures were implemented immediately and are in place to contain displaced material, protect nearby watercourses and minimise any potential environmental impacts.

“We are continuing to conduct detailed technical assessments to establish the cause of the incident and are engaging with relevant authorities and stakeholders as those assessments progress."

A rock berm is an engineered rock structure forming part of the permanent infrastructure at a wind-farm construction site. At Drumnahough, it is designed to contain excavated material generated during construction works.

Loughs Agency

The Loughs Agency subsequently confirmed that it investigated two incidents at the construction site, with the berm breach followed by a separate discharge of dirty water into a watercourse leading to the Elatagh River.

A spokesperson for Loughs Agency said: “We investigated two incidents at a wind-farm construction site last week: a breach in a berm used to hold back stripped peat, followed by a separate discharge of dirty water into a watercourse leading to the Elatagh River. The wind-farm company contained the discharge, and our fishery officers collected samples for analysis.

“We are liaising with the company regarding containment measures at the site and will continue to monitor water quality in the receiving watercourses downstream. Our inspections have found no water-quality issues since the discharge.”

Drumnahough Wind Farm is currently under construction near the townlands of Treankeel, Meenadaura, Carrickalangan and Cark.

The project is being developed on a 50:50 basis by SSE and FuturEnergy Ireland. FuturEnergy Ireland is an equal venture between state-owned forestry company Coillte and electric utility ESB.